Watershed
162.035 km²
Five subbasins, S_1 to S_5, draining toward the Hare Weir.
The Hare HEC-HMS model was prepared as an event-based design-flood model. Each simulation uses the same basin geometry, hydrologic parameters, routing configuration and computational time step. Only the adopted 24-hour design rainfall depth changes with return period.
The table below provides the working register for the principal design-storm simulations. It distinguishes between completed runs and events that have been configured but still require final simulation and result extraction.
| Run ID | Return Period | 24-h Rainfall | Outlet | Status |
|---|---|---|---|---|
| RUN_HARE_10YR | 10 years | 49.61 mm | Sink-1 / Hare Weir | Configured / not yet finalised |
| RUN_HARE_25YR | 25 years | 54.99 mm | Sink-1 / Hare Weir | Configured / result to be confirmed |
| RUN_HARE_50YR | 50 years | 58.98 mm | Sink-1 / Hare Weir | Completed and accepted |
| RUN_HARE_100YR | 100 years | 62.95 mm | Sink-1 / Hare Weir | Configured / not yet finalised |
The final HEC-HMS event simulations use the adopted 24-hour design rainfall depths obtained from the frequency analysis prepared for the Hare watershed.
| Return Period | Adopted 24-h Rainfall | HEC-HMS Event |
|---|---|---|
| 10-year | 49.61 mm | P24,T=10 |
| 25-year | 54.99 mm | P24,T=25 |
| 50-year | 58.98 mm | P24,T=50 |
| 100-year | 62.95 mm | P24,T=100 |
To permit direct comparison among return periods, the basin model and hydrologic parameters are kept unchanged between runs. The design rainfall depth is the principal input that varies.
162.035 km²
Five subbasins, S_1 to S_5, draining toward the Hare Weir.
SCS Curve Number
Weighted Curve Numbers assigned individually to each subbasin.
SCS Unit Hydrograph
Final adopted lags of 118, 76, 65, 52 and 62 minutes for S_1 to S_5.
None
Event simulations represent direct storm runoff.
Muskingum
R_1 and R_2 route the flood hydrograph toward the project outlet.
15 minutes
The same time step is maintained for all design simulations.
24 hours
Synthetic design rainfall is applied over one day.
72 hours
Allows the complete flood hydrograph and recession to pass through the watershed.
The 50-year event was used as the principal completed design simulation during the current stage of the Hare headworks reassessment.
RUN_HARE_50YR
58.98 mm / 24 h
114.4 m³/s
16.84 mm
2.73 million m³
Simulation Day 1 · approximately 16:15
The peak discharge of 114.4 m³/s is reported at Sink-1, the HEC-HMS element representing the Hare Weir and irrigation headworks outlet.
At the time of peak discharge, the routed flow from reach R_2 contributes approximately 111.1 m³/s, while the local contribution from S_4 is approximately 3.2 m³/s. Their combination produces the reported outlet peak.
The 25-year event is configured using the same basin model, loss method, transform parameters, routing parameters, computation interval and simulation duration as the accepted 50-year run.
RUN_HARE_25YR
54.99 mm / 24 h
Sink-1 / Hare Weir
Configured — final outlet result to be confirmed
Once the final 25-year simulation output is confirmed, the outlet peak discharge, runoff depth, runoff volume and peak time should be inserted here so that the 25-year and 50-year hydrographs can be compared directly.
Each simulation should be reproducible from the stored HEC-HMS project by maintaining the following settings.
| Item | Adopted Setting |
|---|---|
| Basin model | Final Hare basin model |
| Total area | 162.035 km² |
| Subbasins | S_1, S_2, S_3, S_4, S_5 |
| Loss method | SCS Curve Number |
| Transform method | SCS Unit Hydrograph |
| Baseflow | None |
| Routing method | Muskingum |
| Computation interval | 15 minutes |
| Storm duration | 24 hours |
| Simulation period | 72 hours |
| Design outlet | Sink-1 / Hare Weir |
A number of preliminary simulations were carried out while the basin lag times, design rainfall and routing representation were being reviewed. Those simulations were useful during model development but should not be treated as final design results.
| Return Period | P24 (mm) | Peak at Hare Weir | Runoff Depth | Status |
|---|---|---|---|---|
| 10 years | 49.61 | — | — | Not yet finalised |
| 25 years | 54.99 | — | — | Result to be confirmed |
| 50 years | 58.98 | 114.4 m³/s | 16.84 mm | Completed / accepted |
| 100 years | 62.95 | — | — | Not yet finalised |
The HEC-HMS design runs provide the flood hydrographs required for the hydraulic assessment of the Hare diversion structure. The outlet hydrograph provides more information than a single peak-flow value, because it also describes the timing, duration and total volume of the flood event.
The final HEC-HMS design results will subsequently be compared with independent SWAT watershed modelling. This provides an additional check on the hydrologic basis adopted for the reconstructed Hare Irrigation Project.