Archived 24-hour rainfall
58.98 mm
Earlier synthetic design-storm input.
The hydrological analysis supports the redesign of the Hare River diversion headworks serving a watershed of approximately 162.035 km². The project has selected 195.2 m³/s as its updated working 50-year flood-design discharge. Previous numerical HEC-HMS outputs remain available below as an archive and are not relabelled as results of the updated event.
2026 preliminary design basis. The revised IMERG-related result has been selected for the new ogee-weir design. Its final HEC-HMS model export, rainfall-frequency inputs, peak timing and outlet hydrograph still require cross-checking before the value can be described as a verified final model result or construction-approved design. The HEC-RAS upstream/downstream boundary hydrographs are separate hydraulic-model outputs, not by themselves proof of the HEC-HMS peak exactly at the weir.
Original 50-year flood estimate.
Older 50-year outlet hydrograph and runoff figures shown below.
Revised flood discharge; final event documentation pending.
For the diversion-weir redesign, the current working flood value is 195.2 m³/s. The result register below deliberately avoids carrying over rainfall, runoff and timing values from a different model run.
| Return period | Updated peak (m³/s) | Updated 24-h rainfall (mm) | Status |
|---|---|---|---|
| 10 years | — | — | Updated simulation not yet supplied |
| 25 years | — | — | Updated simulation not yet supplied |
| 50 years | 195.2 | — | Provisional working design discharge |
| 100 years | — | — | Updated simulation not yet supplied |
The following is the earlier HEC-HMS event-based simulation retained for traceability. These figures describe the previous 114.4 m³/s model run only; they are no longer the governing flood discharge for the redesigned weir.
58.98 mm
Earlier synthetic design-storm input.
114.4 m³/s
Earlier HEC-HMS outlet hydrograph, Sink-1 / Hare Weir.
16.84 mm
Direct runoff from the earlier simulation.
≈ 2.73 million m³
Depth multiplied by 162.035 km².
Simulation Day 1 · approximately 16:15
Synthetic simulation clock, not a historical flood observation.
Sink-1 / Hare Weir
The outlet of the earlier hydrological model.
| Return period | Old rainfall (mm) | Old HEC-HMS peak (m³/s) | Status |
|---|---|---|---|
| 10 years | 49.61 | — | Earlier input; outlet result pending |
| 25 years | 54.99 | — | Earlier input; outlet result not verified here |
| 50 years | 58.98 | 114.4 | Earlier CHIRPS / HEC-HMS run (archived) |
| 100 years | 62.95 | — | Earlier input; outlet result pending |
The following archived outlet hydrograph was an earlier HEC-HMS result used for hydraulic design. It describes not only the maximum flow, but also the timing, duration and recession of the flood wave arriving at the Hare Weir.
At the time of the earlier 114.4 m³/s HEC-HMS outlet peak, most of the discharge arriving at Sink-1 is routed from the upstream watershed through R_2. A smaller local contribution is added from S_4 near the downstream end of the basin model.
≈ 111.1 m³/s
Routed upstream contribution arriving through reach R_2 at the time of the outlet peak.
≈ 3.2 m³/s
Local runoff contribution from S_4 at approximately the same peak time.
The earlier 50-year model event produced a direct runoff depth of 16.84 mm. Applied across the full modelled watershed, this corresponds to approximately 2.73 million m³ of runoff volume.
Runoff Volume = Runoff Depth × Watershed Area
0.01684 m × 162.035 × 106 m² ≈ 2.73 × 106 m³
This volume represents the storm-generated runoff simulated by the event model. Because baseflow is set to None, it should not be interpreted as the total volume of river flow that would occur during the same period in a continuous hydrologic simulation.
The following figures preserve the graphical record of the earlier 50-year HEC-HMS simulation. The design-storm hyetograph is retained here as the rainfall-input reference; the remaining figures document the resulting watershed response and HEC-HMS outputs.
The headworks are being reassessed using the updated working Q50 = 195.2 m³/s instead of the earlier HEC-HMS 114.4 m³/s reference. The 195.2 m³/s value is a flood-passage design input; it must not be confused with the 1.55 m³/s planned irrigation diversion discharge.
The updated design will check crest discharge capacity, flood afflux, approach and tailwater levels at the actual structure, under-sluice operation, canal regulator, sediment exclusion, hydraulic-jump energy dissipation, seepage/uplift, scour and stability. A separate HEC-RAS boundary stage cannot be substituted for a surveyed upstream or downstream stage at the weir axis.
| Assessment | Q50 (m³/s) | Evidence and use |
|---|---|---|
| HARE 1995 | 59.18 | Original historical frequency-analysis design estimate |
| Earlier reconstructed HEC-HMS run | 114.4 | Archived CHIRPS-related event-based output; figures retained above |
| 2026 updated working design | 195.2 | Preliminary design-flood basis; updated event-source documentation to be confirmed |
The updated 195.2 m³/s design discharge is approximately 3.30 times the historical estimate and 1.71 times the older reconstructed HEC-HMS peak. These ratios compare scenarios based on different analysis inputs; they do not by themselves validate the new return period.
See Validation and 1995 Comparison for the historical comparison methodology.
| Output | Current status |
|---|---|
| Updated 50-year headworks design flow | 195.2 m³/s — preliminary working basis |
| Updated IMERG 50-year rainfall depth and frequency fit | Not substantiated by the uploaded event-run export; verification required |
| Updated HEC-HMS outlet hydrograph (195.2 m³/s event) | Not present on this page; obtain the corresponding output |
| Updated event runoff depth, volume and peak time | Pending matching run summary |
| Updated 10-, 25- and 100-year outlet peaks | Pending verified scenario runs |
| Earlier 50-year rainfall input | Archived: 58.98 mm |
| Earlier HEC-HMS 50-year peak | Archived: 114.4 m³/s |
| Earlier HEC-HMS 50-year runoff depth | Archived: 16.84 mm |
| Earlier HEC-HMS event runoff volume | Archived: ~2.73 million m³ |
| Headworks layout and final water levels | Preliminary; local HEC-RAS sections, site survey and foundation checks required |
| Modelled watershed area | 162.035 km² (earlier HEC-HMS basin delineation) |
|---|---|
| Project working flood return period | 50 years (to be verified against revised rainfall analysis) |
| Current working flood-design discharge | 195.2 m³/s |
| Earlier HEC-HMS 50-year peak | 114.4 m³/s (archive only) |
| Historical 1995 50-year design flood | 59.183 m³/s |
| Irrigation diversion requirement | 1.55 m³/s (separate from flood discharge) |
| Headworks design | Ogee weir / under-sluice / intake / energy dissipation |
| Outstanding hydrological results | Updated rainfall, HEC-HMS hydrograph, runoff depth/volume and peak time |
The current project redesign is based on 195.2 m³/s as a provisional flood-passage discharge. Earlier HEC-HMS data remain accessible for transparent comparison without misrepresenting the two model scenarios as a single simulation.