HEC-HMS · HARE Flood Design · Updated 2026

Hydrological Results

The hydrological analysis supports the redesign of the Hare River diversion headworks serving a watershed of approximately 162.035 km². The project has selected 195.2 m³/s as its updated working 50-year flood-design discharge. Previous numerical HEC-HMS outputs remain available below as an archive and are not relabelled as results of the updated event.

Updated 50-year headworks design discharge

Q50 = 195.2 m³/s

2026 preliminary design basis. The revised IMERG-related result has been selected for the new ogee-weir design. Its final HEC-HMS model export, rainfall-frequency inputs, peak timing and outlet hydrograph still require cross-checking before the value can be described as a verified final model result or construction-approved design. The HEC-RAS upstream/downstream boundary hydrographs are separate hydraulic-model outputs, not by themselves proof of the HEC-HMS peak exactly at the weir.

HARE 1995 · Historical design59.18 m³/s

Original 50-year flood estimate.

Earlier HEC-HMS · CHIRPS archive114.4 m³/s

Older 50-year outlet hydrograph and runoff figures shown below.

2026 headworks redesign · Working Q50195.2 m³/s

Revised flood discharge; final event documentation pending.

1. Current Design-Flood Results

For the diversion-weir redesign, the current working flood value is 195.2 m³/s. The result register below deliberately avoids carrying over rainfall, runoff and timing values from a different model run.

10-year · Updated scenarioPending
25-year · Updated scenarioPending
50-year · Working design flow195.2 m³/s
100-year · Updated scenarioPending
Return periodUpdated peak (m³/s)Updated 24-h rainfall (mm)Status
10 years——Updated simulation not yet supplied
25 years——Updated simulation not yet supplied
50 years195.2—Provisional working design discharge
100 years——Updated simulation not yet supplied
Do not mix the two modelling runs. The previous 50-year rainfall of 58.98 mm, 16.84 mm runoff depth, 2.73 million m³ runoff volume, 16:15 model peak time and R_2/S_4 contributions belong to the 114.4 m³/s archive run. Updated values for the 195.2 m³/s event must come from its corresponding model output.

2. Earlier HEC-HMS 50-Year Result — Archived Reference

The following is the earlier HEC-HMS event-based simulation retained for traceability. These figures describe the previous 114.4 m³/s model run only; they are no longer the governing flood discharge for the redesigned weir.

Archived 24-hour rainfall

58.98 mm

Earlier synthetic design-storm input.

Archived outlet peak

114.4 m³/s

Earlier HEC-HMS outlet hydrograph, Sink-1 / Hare Weir.

Archived runoff depth

16.84 mm

Direct runoff from the earlier simulation.

Archived runoff volume

≈ 2.73 million m³

Depth multiplied by 162.035 km².

Archived peak time

Simulation Day 1 · approximately 16:15

Synthetic simulation clock, not a historical flood observation.

Archived model outlet

Sink-1 / Hare Weir

The outlet of the earlier hydrological model.

Earlier frequency-input record

Return periodOld rainfall (mm)Old HEC-HMS peak (m³/s)Status
10 years 49.61 — Earlier input; outlet result pending
25 years 54.99 — Earlier input; outlet result not verified here
50 years 58.98 114.4 Earlier CHIRPS / HEC-HMS run (archived)
100 years 62.95 — Earlier input; outlet result pending

3. Earlier Outlet Hydrograph — Archive

The following archived outlet hydrograph was an earlier HEC-HMS result used for hydraulic design. It describes not only the maximum flow, but also the timing, duration and recession of the flood wave arriving at the Hare Weir.

Archived 50-year outlet result (114.4 m³/s): the earlier simulation reaches a peak discharge of 114.4 m³/s at approximately Day 1 at about 16:15 (synthetic simulation time) at Sink-1 / Hare Weir.
Hare HEC-HMS 50-year outlet flood hydrograph at Sink-1 and Hare Weir showing a peak discharge of 114.4 cubic metres per second
Figure — Archived 50-year HEC-HMS outlet flood hydrograph (114.4 m³/s). This archived hydrograph is an HEC-HMS model output. This earlier model figure shows the rise, peak and recession of the simulated flood wave produced by the earlier 50-year design storm.

4. Archived Flow Contributions at the Earlier Outlet Peak

At the time of the earlier 114.4 m³/s HEC-HMS outlet peak, most of the discharge arriving at Sink-1 is routed from the upstream watershed through R_2. A smaller local contribution is added from S_4 near the downstream end of the basin model.

R_2 Routed Flow

≈ 111.1 m³/s

Routed upstream contribution arriving through reach R_2 at the time of the outlet peak.

S_4 Local Contribution

≈ 3.2 m³/s

Local runoff contribution from S_4 at approximately the same peak time.

Rounding: the component values are reported approximately, so their rounded sum may differ slightly from the archived HEC-HMS outlet peak of 114.4 m³/s.

5. Archived Runoff Depth and Volume

The earlier 50-year model event produced a direct runoff depth of 16.84 mm. Applied across the full modelled watershed, this corresponds to approximately 2.73 million m³ of runoff volume.

Volume check

Runoff Volume = Runoff Depth × Watershed Area

0.01684 m × 162.035 × 106 m² ≈ 2.73 × 106 m³

This volume represents the storm-generated runoff simulated by the event model. Because baseflow is set to None, it should not be interpreted as the total volume of river flow that would occur during the same period in a continuous hydrologic simulation.

6. Archived HEC-HMS Model Figures

The following figures preserve the graphical record of the earlier 50-year HEC-HMS simulation. The design-storm hyetograph is retained here as the rainfall-input reference; the remaining figures document the resulting watershed response and HEC-HMS outputs.

Input versus result: the design-storm hyetograph is an HEC-HMS input. The outlet hydrograph, element peak flows, runoff depth and volume, and simulation summary are HEC-HMS results.
Image archive notice: Every figure below comes from the older HEC-HMS scenario that produced 114.4 m³/s. No figure below is a hydrograph of the updated 195.2 m³/s event.

7. Engineering Interpretation and Headworks Redesign

The headworks are being reassessed using the updated working Q50 = 195.2 m³/s instead of the earlier HEC-HMS 114.4 m³/s reference. The 195.2 m³/s value is a flood-passage design input; it must not be confused with the 1.55 m³/s planned irrigation diversion discharge.

The updated design will check crest discharge capacity, flood afflux, approach and tailwater levels at the actual structure, under-sluice operation, canal regulator, sediment exclusion, hydraulic-jump energy dissipation, seepage/uplift, scour and stability. A separate HEC-RAS boundary stage cannot be substituted for a surveyed upstream or downstream stage at the weir axis.

Design status: Preliminary hydraulic design. The final rainfall-frequency fit, updated hydrograph export, actual weir-section geometry and site-level hydraulics must be verified before issuing construction dimensions.
View HARE diversion-weir and headworks design →
Preliminary HARE ogee diversion weir infographic for working 50-year flood design Q = 195.2 cubic metres per second
Figure — HARE diversion-weir and headworks preliminary concept (Q50 = 195.2 m³/s). This is a concept infographic, not a certified hydraulic or construction drawing. Diagram annotations and local design levels remain subject to verification.

8. Historical and Reconstructed 50-Year Flood Comparison

AssessmentQ50 (m³/s)Evidence and use
HARE 199559.18Original historical frequency-analysis design estimate
Earlier reconstructed HEC-HMS run114.4Archived CHIRPS-related event-based output; figures retained above
2026 updated working design195.2Preliminary design-flood basis; updated event-source documentation to be confirmed

The updated 195.2 m³/s design discharge is approximately 3.30 times the historical estimate and 1.71 times the older reconstructed HEC-HMS peak. These ratios compare scenarios based on different analysis inputs; they do not by themselves validate the new return period.

See Validation and 1995 Comparison for the historical comparison methodology.

9. Result Verification Register

OutputCurrent status
Updated 50-year headworks design flow195.2 m³/s — preliminary working basis
Updated IMERG 50-year rainfall depth and frequency fitNot substantiated by the uploaded event-run export; verification required
Updated HEC-HMS outlet hydrograph (195.2 m³/s event)Not present on this page; obtain the corresponding output
Updated event runoff depth, volume and peak timePending matching run summary
Updated 10-, 25- and 100-year outlet peaksPending verified scenario runs
Earlier 50-year rainfall inputArchived: 58.98 mm
Earlier HEC-HMS 50-year peakArchived: 114.4 m³/s
Earlier HEC-HMS 50-year runoff depthArchived: 16.84 mm
Earlier HEC-HMS event runoff volumeArchived: ~2.73 million m³
Headworks layout and final water levelsPreliminary; local HEC-RAS sections, site survey and foundation checks required

10. Summary and Design Use

Modelled watershed area162.035 km² (earlier HEC-HMS basin delineation)
Project working flood return period50 years (to be verified against revised rainfall analysis)
Current working flood-design discharge195.2 m³/s
Earlier HEC-HMS 50-year peak114.4 m³/s (archive only)
Historical 1995 50-year design flood59.183 m³/s
Irrigation diversion requirement1.55 m³/s (separate from flood discharge)
Headworks designOgee weir / under-sluice / intake / energy dissipation
Outstanding hydrological resultsUpdated rainfall, HEC-HMS hydrograph, runoff depth/volume and peak time

The current project redesign is based on 195.2 m³/s as a provisional flood-passage discharge. Earlier HEC-HMS data remain accessible for transparent comparison without misrepresenting the two model scenarios as a single simulation.