HEC-HMS · Technical workspace

Basin Model

The Hare River watershed was represented in HEC-HMS as five hydrologic subbasins connected through junctions and two routed river reaches to the Hare irrigation diversion site. The final modelled drainage area at the Hare Weir outlet is 162.035 km².

Model outlet: The downstream HEC-HMS element is Sink-1, representing the Hare Weir / irrigation headworks location where the final design hydrograph and peak discharge are extracted.

1. Basin Model Development

The basin model was constructed from the GIS-based watershed delineation. Terrain information from the Digital Elevation Model (DEM) was used to identify drainage direction, stream paths, subbasin boundaries and the river network draining toward the Hare diversion site.

The watershed was divided into five hydrologically connected subbasins, designated S_1 to S_5. Two principal river segments, R_1 and R_2, represent the routed sections of the main drainage system. Junction elements combine runoff generated in different parts of the watershed before the flow reaches the project outlet.

5 Subbasins

S_1, S_2, S_3, S_4 and S_5 represent the hydrologically delineated drainage areas contributing to the Hare River.

2 Routed Reaches

R_1 and R_2 represent the principal river sections through which upstream flood hydrographs are translated and attenuated.

Hare Weir Outlet

Sink-1 represents the final HEC-HMS outlet at the Hare irrigation diversion and headworks site.

2. Delineated Subbasins

The final GIS delineation produced five subbasins with a combined area of 162.035 km². The largest unit is S_1, which accounts for almost half of the entire modelled watershed.

Subbasin Area (km²) Share of Watershed HEC-HMS Element
S_1 77.065 47.56% Subbasin
S_2 25.498 15.74% Subbasin
S_3 25.502 15.74% Subbasin
S_4 13.533 8.35% Subbasin
S_5 20.437 12.61% Subbasin
Total 162.035 100% Hare Watershed

The use of separate subbasins allows rainfall losses and runoff response to vary spatially rather than treating the entire Hare watershed as one lumped catchment.

3. Subbasin Hydrologic Parameters

Each HEC-HMS subbasin was assigned its own drainage area, weighted Curve Number and runoff lag. These parameters were derived from the GIS watershed analysis, land-use distribution, hydrologic soil grouping and drainage geometry.

Subbasin Area (km²) Weighted CN Final Lag (min) Loss Method Transform
S_1 77.065 78.26 118 SCS Curve Number SCS Unit Hydrograph
S_2 25.498 78.94 76 SCS Curve Number SCS Unit Hydrograph
S_3 25.502 75.63 65 SCS Curve Number SCS Unit Hydrograph
S_4 13.533 74.62 52 SCS Curve Number SCS Unit Hydrograph
S_5 20.437 78.60 62 SCS Curve Number SCS Unit Hydrograph
Important: The basin model geometry determines where runoff is produced and how it enters the drainage network. The hydrologic methods assigned to these elements are documented separately on the Methods & Parameters page.

4. River Reach Representation

Two principal reaches were retained in the HEC-HMS basin model. R_1 is the longer upstream routing reach, while R_2 forms the shorter downstream reach immediately upstream of the Hare diversion area.

Reach lengths and longitudinal slopes were obtained from the GIS drainage network and DEM-derived elevation characteristics.

Reach Length (m) Length (km) Average Slope Adopted Manning n Routing
R_1 10,377.24 10.377 0.112458 0.050 Muskingum
R_2 4,745.09 4.745 0.033298 0.040 Muskingum

R_1 is approximately 10.38 km long, whereas R_2 is approximately 4.75 km. The substantially steeper average gradient of R_1 reflects the upper part of the drainage system, while the lower reach becomes less steep as the river approaches the Hare irrigation area.

5. Junctions and Network Connectivity

HEC-HMS junction elements were used to combine runoff from different portions of the watershed and to transfer the resulting hydrograph into the downstream routing reaches.

Established Main Routing Sequence

Upstream Subbasins → J_1 → R_1 → J_2 → R_2 → Hare Weir / Sink-1

Subbasins S_2 and S_5 contribute to the upstream junction J_1. Their combined hydrograph is routed through R_1 toward the lower part of the watershed.

Additional subbasin runoff enters the main drainage network as represented by the final HEC-HMS basin schematic. The routed upstream flow then passes through J_2 and R_2 before reaching the project outlet.

At the downstream end of the model, runoff from S_4 is combined with the routed flow arriving through R_2 before the total hydrograph is reported at Sink-1.

Network documentation: Only connections confirmed in the completed HEC-HMS model are stated explicitly here. The graphical basin model remains the authoritative representation of the complete element-to-element connectivity.

6. Hare Weir Model Outlet

The final model outlet is represented in HEC-HMS by Sink-1. This location corresponds to the Hare irrigation diversion / weir site and was selected because the main purpose of the hydrologic model is to estimate the flood hydrograph reaching the proposed or reconstructed headworks.

Outlet Name

Sink-1

HEC-HMS terminal element representing the Hare project outlet.

Contributing Area

162.035 km²

Total drainage area represented by subbasins S_1 to S_5.

Engineering Location

Hare Weir / Headworks

Design-flow extraction point for hydraulic assessment of the diversion works.

Primary Output

Discharge Hydrograph

Provides peak discharge, timing of peak, runoff volume and the complete flood hydrograph.

7. GIS and DEM-Derived Information

The basin model was developed from spatial data rather than by manually assigning arbitrary drainage areas. GIS processing provided the basic geometric framework required by HEC-HMS.

Model Information Derivation / Use
Watershed boundary Delineated from the DEM using the Hare diversion site as the downstream control point.
Subbasin boundaries Derived from terrain-controlled drainage divides.
Subbasin areas GIS-calculated areas for S_1 to S_5.
Drainage network Derived from DEM flow direction and flow accumulation.
Reach lengths Measured along the GIS-derived main river network.
Reach slopes Derived from the elevation change along each river reach.
Land use Used with hydrologic soil information to calculate weighted Curve Numbers for each subbasin.
Outlet Positioned at the Hare Weir / irrigation headworks.

8. HEC-HMS Basin Model Schematic

The figure below presents the final HEC-HMS basin-model configuration for the Hare River watershed. It shows the five subbasins S_1–S_5, the two junctions J_1 and J_2, routed reaches R_1 and R_2, and the downstream Sink-1 / Hare Weir outlet.

The schematic also summarizes the drainage area of each subbasin and the lengths of the two principal routed river reaches. Together, these elements define how runoff generated throughout the 162.035 km² watershed is combined and routed toward the Hare irrigation headworks.

Model-network interpretation: subbasin runoff is transferred through junctions and river reaches before reaching Sink-1. Junction peak discharges are model outputs and should only be added to the figure after the corresponding HEC-HMS result tables have been confirmed.
Hare HEC-HMS basin model schematic showing subbasins S_1 to S_5, junctions J_1 and J_2, reaches R_1 and R_2, and Sink-1 at the Hare Weir outlet
Figure — Hare HEC-HMS basin model schematic. Five subbasins with a total drainage area of 162.035 km² are connected through J_1 and J_2 and routed along R_1 (10.377 km) and R_2 (4.745 km) to Sink-1 / Hare Weir. Subbasin areas are S_1 = 77.065 km², S_2 = 25.498 km², S_3 = 25.502 km², S_4 = 13.533 km² and S_5 = 20.437 km².

9. Basin Model Summary

Total Watershed Area 162.035 km²
Subbasins 5 — S_1, S_2, S_3, S_4, S_5
Largest Subbasin S_1 — 77.065 km²
River Reaches 2 — R_1 and R_2
R_1 Length 10.377 km
R_2 Length 4.745 km
Junctions J_1 and J_2
Routing Method Muskingum
Downstream Element Sink-1
Engineering Outlet Hare Weir / Irrigation Headworks

This basin configuration forms the spatial framework for the HEC-HMS rainfall-runoff simulations. Design precipitation is applied to each subbasin, rainfall excess is transformed into direct runoff, the resulting hydrographs are combined and routed through the river network, and the final design hydrograph is obtained at the Hare Weir.